Short answer: in India, the main Coconut Development Board (CDB) support for a commercial coconut processing unit is the Technology Mission on Coconut (TMoC). Under its “adoption of technologies for processing and product diversification” component, approved projects receive a back-ended, credit-linked capital subsidy of 25% of the eligible project cost. The rate is 33.3% for SC/ST women farmers and 50% for high-value agriculture in the Andaman & Nicobar Islands and Lakshadweep. The maximum is ₹500 lakh per project, according to CDB’s current operational guidelines (2026 edition). The subsidy is calculated on eligible cost, not total cost, and it is released only through the financing bank. How you structure the project report and your machinery quotations therefore affects how much you can actually claim.

This guide is for entrepreneurs, FPOs and consultants planning coconut processing units in India. It summarises the TMoC rules that matter at planning stage, works through an illustrative eligible-cost calculation and lists what to ask your equipment supplier for. It is not legal or financial advice; CDB has sole discretion, so confirm current rules with the Board before committing money.
Why this matters now
CDB co-hosted the 62nd International Coconut Community Session and Ministerial Meeting in Kochi from 17 to 20 November 2026. Value addition was among the priorities named at the opening, and the Union Agriculture Secretary said the industry must respond to changing consumer preferences and international market requirements (The New Indian Express, 18 November 2026). TMoC is CDB’s main instrument for financing processing capacity. The scheme has been revised over time: an older CDB advertisement still online describes the processing subsidy as 25% “limited to Rs.50 lakh”. The current operational guidelines state a maximum of ₹500 lakh. Work from the current guidelines, not old brochures.
Which scheme fits which project
| Scheme | Who it suits | Assistance (as published) | How it is paid |
|---|---|---|---|
| CDB TMoC – adoption of processing technologies | New units making value-added coconut products, financed by a term loan | 25% of eligible project cost (33.3% SC/ST women farmers; 50% A&N and Lakshadweep high-value agriculture), maximum ₹500 lakh | Back-ended, credit-linked; held in a subsidy reserve fund at the lending bank |
| CDB Kalpa Hastha | Small entrepreneurs who completed CDB training or technology transfer and already run a unit | 50% reimbursement, maximum ₹3 lakh | Reimbursement after inspection; apply within 12 months, with at least 6 months of documented sales |
| CDB primary processing centres | FPOs and farmers making ball copra or milling copra, or minimally processing tender coconut | Up to ₹3 lakh | Against expenditure, per guideline conditions |
| MoFPI PMFME (individual micro units) | Micro food processing enterprises, including coconut products | 35% credit-linked capital subsidy, maximum ₹10 lakh per unit | Credit-linked; beneficiary contributes at least 10% |
The TMoC guidelines allow central plus state assistance for the same project only if the total does not exceed 50% of eligible project cost. Subsidy from two central government organisations for the same project is not admissible. So you would normally choose either TMoC or PMFME for a given project, not both.
Planning a CDB-assisted coconut processing unit? Request a quotation from GTI.
Tell us your product, target capacity, raw-material data and site location. GTI Group engineers will review it and prepare a proposal for your project, in India or abroad.
TMoC conditions that shape the project report
These conditions, from the TMoC chapter of the guidelines, decide what your detailed project report (DPR) should look like.
- Financing structure: at least 40% of total project cost must come from a term loan from a scheduled bank, NABARD or NEDFi, and at least 25% from the promoter.
- Timing: applications received more than 10 months after the term loan sanction date are not considered. Expenses incurred before term loan sanction are not eligible.
- Land: owned, or leased for at least 15 years under a registered lease. Land cost itself is not eligible.
- Building: no more than 40% of eligible project cost, and capped by area and rate norms (see below).
- Preliminary and pre-operative cost: no more than 1% of eligible project cost.
- Net worth: the applicant’s combined net worth must be at least 1.5 times the subsidy sought.
- Product: the guidelines say only processing units with innovative products will be considered, and that expansion projects for value addition or modernisation will not be considered. Elsewhere, they mention physical verification for expansion projects. If you are expanding an existing plant, ask CDB how these provisions apply to you before preparing the DPR.
- Not eligible: land; plant and machinery not directly related to the project; second-hand, refurbished or reconditioned machines; computers and office furniture; CCTV and security systems; stationery and consumables; working capital; and weighbridges. Only essential laboratory equipment is considered. A technical know-how fee can be included.
Cost norms that cap individual items
Even an eligible item is only counted up to the guideline norm. The ones that most often bite in coconut projects are:
| Item | Norm in the TMoC guidelines |
|---|---|
| Building rate | RCC framed ₹2,500/sq ft; composite ₹1,700/sq ft; pre-fabricated or truss ₹1,500/sq ft |
| Building area, nut-based units | 5,000 nuts/day: 5,000 sq ft; 10,000: 7,000; 20,000: 11,000; 30,000: 14,000; 40,000: 16,000; 50,000: 18,000 sq ft |
| Building area, shell products | Activated carbon 5–15 t/day: 10,000–20,000 sq ft; shell charcoal/powder 3–20 t/day: 5,000–10,000 sq ft |
| Electrification | 12% of eligible machinery cost |
| DG set / transformer | ₹10,000 per kVA / ₹9,000 per kVA |
| Effluent treatment plant | ₹75,000 per KLD up to 50 KLD, then ₹60,000 per KLD to 100 KLD, then ₹50,000 per KLD |
| Solar; fire systems | ₹55,000 per kWp; ₹250–1,200 per sqm depending on system |
Note that building area is keyed to nuts per day. Your DPR, layout and machinery quotations must therefore state capacity on the same basis. If a dryer quotation is written in kg/h of output and the DPR in nuts/day, reconcile them with a mass balance first. Our worked desiccated coconut plant sizing example shows how to convert between the two.
Illustrative eligible-cost calculation
Illustrative example only. All costs below are assumptions chosen to show the method. They are not GTI prices, typical costs or a CDB assessment.
Assume a new desiccated coconut unit of 20,000 nuts/day with an RCC building:
| Item | Project cost (₹ lakh) | Counted as eligible (₹ lakh) | Reason |
|---|---|---|---|
| Land | 60 | 0 | Land not eligible |
| Building, 12,000 sq ft at ₹2,800/sq ft | 336 | 275 | Area capped at 11,000 sq ft × ₹2,500 |
| New plant and machinery | 400 | 400 | Directly related, new |
| Electrification | 60 | 48 | Capped at 12% of machinery |
| DG set, 250 kVA | 30 | 25 | ₹10,000/kVA |
| ETP, 30 KLD | 25 | 22.5 | ₹75,000/KLD |
| Essential laboratory equipment | 10 | 10 | Assumed essential |
| Computers, furniture, CCTV | 8 | 0 | Excluded |
| Preliminary and pre-operative | 15 | about 7.9 | Capped at 1% of eligible cost |
| Working capital margin | 50 | 0 | Excluded |
| Total | 994 | about 788 |
Checks: the building is about 35% of eligible cost, so within the 40% limit. At 25%, the subsidy would be about ₹197 lakh. That is about 20% of the total project cost, not 25%. The term loan would have to be at least ₹398 lakh (40% of ₹994 lakh), and the promoter contribution at least ₹249 lakh (25%). The applicant’s net worth would need to be at least 1.5 × ₹197 lakh, or about ₹296 lakh. Build this eligible-cost table at DPR stage, not after bank sanction.
How the subsidy is released
- The DPR goes to CDB’s Internal Screening Committee, then to the Project Approval Committee (PAC) chaired by the Board’s CEO.
- After PAC approval, the promoter, CDB and the bank sign a tripartite memorandum of understanding.
- First 50% of the eligible subsidy is released after the MoU, a preliminary inspection and drawal of 50% of the term loan.
- Second 50% follows a joint inspection by CDB and the bank, full drawal of the loan, building completion and machinery installation certificates, and commercial production at a minimum of 30% capacity utilisation.
- The subsidy is kept in a subsidy reserve fund account with the bank, with a five-year lock-in. It can be adjusted against the loan only after the non-subsidy portion is repaid, and after a minimum of three years.
Second-instalment documents include six months of production statements, a quality test report from CDB’s Institute of Technology (Vazhakulam, Aluva) or an NABL-accredited laboratory, an FSSAI licence where applicable, product samples and bank-certified machinery invoices. Plan laboratory, quality records and commissioning around this list.
What to ask your machinery supplier for
Because the bank appraisal and CDB scrutiny both rely on supplier quotations, ask for these from the start:
- Itemised quotations that separate process machinery, electrical works, utilities (boiler or hot-air generator, compressor, DG), laboratory items and any technical know-how fee. Lump sums make it hard to apply the cost norms.
- New equipment only, with a statement to that effect. Refurbished machines are excluded.
- Capacity stated consistently as nuts/day, wet feed, finished output and water evaporation, so the DPR, building-area norm and dryer sizing agree.
- Utility schedules: connected electrical load (for the transformer and DG norms), thermal demand and fuel, water use and effluent volume in KLD (for the ETP norm).
- Layout drawings supporting the building area claimed, and installation certificates the bank can certify.
GTI’s turnkey coconut project scope covers feasibility and product consultation, process design, plant layout and utility planning, machinery manufacturing, installation, commissioning and operator training. For a desiccated coconut unit, see the desiccated coconut machinery and plant page. For VCO and milk products, see the virgin coconut oil machinery and coconut milk processing plant pages. Our sister site describes the desiccated coconut line from a food-plant perspective, and the dryer options are explained on gtidryers.com under coconut drying systems. GTI does not process subsidy applications and cannot promise approval. We can provide itemised quotations, mass balances and layouts in a form your consultant and bank can use.
Common mistakes
- Paying for machinery before term loan sanction, or letting the 10-month application window lapse.
- Building more area than the nuts/day norm allows, or budgeting 25% of total rather than eligible cost.
- Under-planning the 30% utilisation milestone, which depends on nut supply. See our raw-material cost outlook.
FAQ
Is the TMoC subsidy paid in cash to the promoter?
No. It is credit-linked and back-ended. It sits in a subsidy reserve fund with the lending bank and is adjusted against the loan after the lock-in conditions are met.
Which products are covered?
CDB’s scheme advertisement lists examples such as desiccated coconut, VCO, coconut milk and milk powder, tender coconut water, shell powder, charcoal and activated carbon. Confirm your product with CDB, as the guidelines also require “innovative products”.
Related guides and GTI equipment
This guide is part of GTI’s coconut processing series. Related reading and equipment:
- which coconut line to build first: choosing the product.
- raw-material cost signals: operating cost side.
- the quotation data sheet: quotes in a form a subsidy file needs.
- GTI desiccated coconut plant: common first line.
- GTI DC machinery on foodtechprojects.com: group page.
Sources
- Coconut Development Board, Schemes of Coconut Development Board – Operational Guidelines (Prabhat Kumar, Hanumanthe Gowda and Pramod P Kurian, 2026), Part B Technology Mission on Coconut, pp. 109–120; Kalpa Hastha, section A.4.d; primary processing centres, section A.5.a.8. Read on 20 November 2026.
- Coconut Development Board, Schemes page (last updated 19 November 2026).
- Coconut Development Board, Financial Assistance for Coconut Based Industries (earlier advertisement, ₹50 lakh cap).
- Ministry of Food Processing Industries, PMFME scheme page.
- The New Indian Express, Union minister calls for international cooperation among coconut growing nations, 18 November 2026.
About this article
Prepared by the Genex Tech Industries LLP (GTI Group) editorial team from the CDB and MoFPI documents listed above, as read on 20 November 2026. Scheme rules change. The worked example uses assumed costs and is not a CDB assessment. Confirm all conditions with the Coconut Development Board and your lending bank.
Plan your coconut processing project with GTI
GTI Group, engineering since 1985, designs and supplies coconut processing plants and drying systems. Tell us your product, capacity in nuts per day and site details, and we can prepare an itemised equipment scope and mass balance for your project report.
Request a quotation for a CDB-assisted coconut processing unit
Send your capacity, product specification and site details through our quotation request form, and GTI Group will respond with a proposal.
For more information, email mktg@coconutprojects.com or call or WhatsApp us on +91-87774 75596.